Thai Global FreightImporting Green Coffee Beans to Thailand: Permits Guide
Importing green coffee beans into Thailand as of November 2026: DFT permission and quota, plant quarantine, FDA, HS 0901.11 and container logistics.
On this page
- 01What does importing green coffee beans into Thailand require?
- 02How does the Department of Foreign Trade control coffee imports?
- 03WTO in-quota, ASEAN origin and other origins: which route applies?
- 04What does plant quarantine require for green coffee?
- 05Does a green coffee importer need a Thai FDA licence?
- 06How is green coffee classified and charged duty at Thai Customs?
- 07What is the order of work for a first green coffee import?
- 08What documents does a green coffee import need?
- 09How should green coffee be packed, loaded and shipped?
- 10Which Incoterm and contract terms protect a coffee importer?
- 11When should you talk to a forwarder, and what can Thai Global Freight do?
Quick Answer
Importing green coffee beans into Thailand means clearing three separate gates before the goods arrive: import permission from the Department of Foreign Trade (DFT), which controls coffee imports and manages the WTO in-quota allocation; a plant quarantine permit from the Department of Agriculture (DOA); and a check with the Thai FDA on whether a food import premises licence applies to your use. Unroasted beans are classified under HS 0901.11 at Thai Customs. Rules, quotas and duty rates change, so confirm each one in writing with the agency before you pay a supplier.
Key Takeaways
- Coffee is a controlled import: import permission from the Department of Foreign Trade comes before the purchase order, not after the container is booked.
- Origin decides the route: WTO in-quota allocation, ASEAN-origin treatment and other origins each follow different conditions that you confirm with the DFT.
- Plant quarantine is a separate permit from the Department of Agriculture, filed through the national single window, and it depends on the origin country and the product.
- Green coffee is hygroscopic and absorbs odours, so container condition, liners and ventilation matter as much as the paperwork.
- A forwarder coordinates booking, container choice and customs filing, but permits are issued by the agencies and must match the invoice and bill of lading.
What does importing green coffee beans into Thailand require?
Green coffee beans are the dried, unroasted seeds of the coffee plant. As of November 2026, bringing them into Thailand involves three government gates and one customs step, and all of them should be settled before the cargo leaves the origin country. First, the Department of Foreign Trade (DFT) under the Ministry of Commerce controls coffee as a regulated import, so you need import permission and, for the WTO route, a place in the in-quota allocation. Second, the Department of Agriculture (DOA) runs plant quarantine and issues the import permit for plant material through its national single window system. Third, the Food and Drug Administration (Thai FDA) decides whether your activity needs a food import premises licence. Finally, Thai Customs classifies the beans, assesses duty and releases the cargo.
The practical consequence is that an importer cannot treat coffee like an ordinary commercial good. A buyer who negotiates a price with a supplier, pays a deposit and then asks what permits are needed may find that the quota route has closed, that the origin country is not eligible for the route the buyer planned, or that the beans cannot be released at arrival. This guide walks through the gates in order, then covers classification, documents, container logistics and the contract terms that decide who carries risk. It does not quote rates or fees, because those change and depend on origin and quantity. Where a rule could not be confirmed from an official page we fetched, we say what to ask and whom to ask.
How does the Department of Foreign Trade control coffee imports?
The DFT is the agency that decides whether a trader may bring coffee into Thailand. According to the DFT briefing slides we reviewed, coffee imports are managed under the Royal Decree on controlled imports, B.E. 2496 (1953), as amended, which lets the Ministry of Commerce require permission for listed goods. A permit holder is expected to import within the conditions written on the permit, and customs compares the declaration with it at arrival. The slides date from 2020, so treat them as a description of how the system was built, not as today's operating manual; the current conditions must be confirmed on the DFT website or by contacting the relevant DFT division.
What to ask the DFT before you commit to a supplier is short. Which route applies to the origin country of your beans: the WTO in-quota route, the ASEAN route, or the general route for other origins? Is permission granted per shipment or for a period, and what does the permit say about quantity, origin and port of entry? Does the permit have to be in hand before the goods ship, or only before arrival? What happens if the declared quantity differs from the permit? Write down the answers, with the date and the name of the officer, because they become part of your compliance file.
The DFT also publishes announcements about in-quota allocation. One announcement we fetched covers the WTO allocation round for a recent period and shows how the office announces application windows; it is a good example of why timing matters, because the window can be narrow and an application outside it is simply too late for that round.
WTO in-quota, ASEAN origin and other origins: which route applies?
Thailand's WTO commitments set a quantity of certain agricultural goods that can enter at a lower in-quota duty rate, and the DFT allocates that quantity among applicants. In the material we reviewed, applicants register and apply through the DFT's Smart-I electronic system, and an approved applicant receives a certificate of in-quota tax entitlement that customs uses to apply the in-quota treatment. We did not verify whether coffee is in the current in-quota list or what the current allocation rules are, so the first question for the DFT is whether your product and origin fall in the in-quota list at all.
Beans outside the quota route face the out-of-quota conditions or the rules for their specific origin. For origin countries in ASEAN, press reports and DFT webboard answers mention an ASEAN route under the AFTA and ATIGA preferences, but we did not find an official page that states the current conditions for coffee, so we cannot assert them. A Form D certificate of origin is the document that normally supports an ATIGA claim; our guide What is Form D under ATIGA explains how it works, and Types of certificate of origin shows the other certificate families. Whether Form D alone satisfies the DFT for coffee, or whether a separate DFT permit is still required, is exactly the question to put to the DFT in writing.
A simple decision rule helps. Choose the in-quota route when the DFT confirms your origin and product qualify and an application window is open; ask about the ASEAN route when your beans are grown and processed in an ASEAN member state and you can produce origin evidence from the producer; and treat every other origin as a case-by-case question for the DFT before any order is placed. Do not rely on a supplier's statement that coffee can be imported freely, because the supplier is not the Thai authority.

What does plant quarantine require for green coffee?
Thailand regulates the import of plants and plant products to keep pests and diseases out, and the Department of Agriculture runs that control. The DOA's national single window manual for import permit operators describes how an importer registers, submits an application for a plant quarantine import permit and tracks the result electronically, and the DOA announcement we reviewed lists the information an application must carry, including the commodity, origin country, exporter, quantity and entry port. The permit forms are commonly referred to by their Thai form numbers, Por Kor 2 and Por Kor 2-1 (พ.ก.2 and พ.ก.2-1) in the material we read.
We could not open the DOA page that specifically addresses coffee, because the site returned a certificate error when fetched. We therefore cannot say whether green coffee beans from your origin country are prohibited, restricted or free of conditions, or whether a phytosanitary certificate from the origin country's plant protection authority is required. Do not guess. Ask the DOA plant quarantine office, in writing, three things: the status of green coffee beans from your origin; the documents required with the application; and whether inspection takes place at the port of entry.
The plant quarantine permit and the DFT permission are separate. One does not replace the other, and both should name the same importer, origin and commodity. A mismatch, such as a different exporter name on the quarantine permit and on the invoice, is a common reason for cargo to wait at the port while the paperwork is corrected.
Who decides what on a green coffee import
| Party | What it decides | Sort out |
|---|---|---|
| Department of Foreign Trade (DFT) | Import permission for coffee; WTO in-quota allocation and certificate | Before you place the order |
| Department of Agriculture (DOA) plant quarantine | Plant quarantine permit and entry inspection; confirm the status of green coffee | Before the goods ship |
| Thai FDA, Food Division | Whether a food import premises licence applies to your use | Before the goods arrive |
| Thai Customs Department | HS classification, duty by origin, declaration and release | At arrival |
| Freight forwarder and customs broker | Booking, container, documents and filing; does not issue permits | Throughout |
Does a green coffee importer need a Thai FDA licence?
The Thai FDA regulates food imports under the Ministry of Public Health. Its food division describes a licensing procedure for entrepreneurs who import food for sale, and in the material we read the licence for an importing premises is referred to by form numbers such as Or 6 and Or 7 (อ.6 and อ.7). Whether your business needs that licence depends on what you do with the beans. A roaster that imports green coffee and sells roasted coffee to the public is in a different position from a trader who imports beans only as an agricultural commodity for onward sale, and a company importing a sample for testing is different again.
We cannot tell you from the pages we fetched which of those situations is exempt or which product-specific checks apply to green coffee. Ask the FDA food division, with a description of your business and the intended use, whether an import premises licence is needed, whether the shipment needs to be notified or sampled at arrival, and what labelling is required if the beans are sold in retail packs. Bring the answer to your forwarder in writing, because the customs broker will need to know which agency documents to attach to the import declaration.
If you plan to roast and pack for retail, the FDA questions grow: the roasted product and its labels are food products with their own rules. That is outside the scope of this guide, which stops at the green bean entering Thailand and being released to your warehouse.

How is green coffee classified and charged duty at Thai Customs?
The Thai Customs Department classifies goods under the tariff based on the Harmonized System, and unroasted coffee that is not decaffeinated falls under HS 0901.11 in the standard international structure. Roasted coffee sits under a different subheading, and so does coffee with the caffeine removed, which is why the declaration must describe the goods accurately as green, unroasted beans. Our guide What is an HS code explains how the six-digit international code relates to the longer national tariff line, and Customs advance ruling for HS codes in Thailand describes how an importer can ask for a written classification before the first shipment.
Duty depends on origin and on whether the goods enter under the in-quota route, a preferential agreement or the general rate. We are not quoting percentages because the applicable rate is set by the tariff schedule and any preference claimed, and it changes. The practical steps are to ask your customs broker for the current rate for your exact tariff line and origin, to ask whether VAT and any other charges apply, and to run the result through the landed cost calculator before you agree a price. The article How import duty and VAT are calculated in Thailand shows the order of the calculation.
At arrival, the broker files the import declaration and attaches the permits. Customs compares the declaration against the DFT permit, the quota certificate if the in-quota route is used, the origin evidence and the transport documents. Any difference in description, quantity or importer name can hold the cargo, so the data on every document must agree before the vessel sails.
What is the order of work for a first green coffee import?
The order matters more than any single step, because several approvals depend on facts that are fixed by the supplier contract. Start by confirming the HS code and the true origin of the beans, since origin decides the permission route. Next, speak to the DFT about the route and the timing of any application window. Then confirm plant quarantine requirements with the DOA, and ask the FDA whether your use needs a premises licence. Only when those answers are in writing should you agree the sale contract, the Incoterm, the sample approval and the shipping documents with the supplier. After that comes booking and shipping, and finally customs clearance and any follow-up report that the permit conditions require.
The reason for this order is cost of failure. A mistake at the first three steps can make the whole shipment unimportable, while a mistake at booking can usually be repaired with a change of container or sailing. Keep one shared file for the importer, the supplier and the forwarder, with the permits, the correspondence with each agency and the draft documents, so that the same version of the facts is used everywhere.
Time your first order realistically. Allocation windows, permit processing and the supplier's lead time for lots can each take longer than expected, and we have not verified processing times for any agency, so ask each one for its current service standard instead of planning around a number you found online.
Order of work for a first green coffee import
- 1
Confirm HS code and origin
Unroasted beans sit under HS 0901.11; origin decides the permission route.
- 2
Confirm the DFT route
WTO in-quota, ASEAN or another origin each has its own conditions.
- 3
Confirm plant quarantine
Ask the DOA about the permit form and phytosanitary certificate.
- 4
Confirm the FDA position
Clarify whether your use needs a food import premises licence.
- 5
Agree contract and documents
Incoterm, sample approval, certificates and packing written into the order.
- 6
Book and ship
Dry container inspected for odour, dampness and damage before stuffing.
- 7
Clear customs and report
Match the declaration to the permit and file any required import report.
What documents does a green coffee import need?
The document set is built around one rule: every document must describe the same importer, the same exporter, the same origin, the same commodity and a quantity that fits the permit. The commercial invoice and packing list give the description, the number of bags and the weights. The bill of lading for sea freight, or the air waybill for air, names the consignee and notify party; both should match the importer on the permits. A certificate of origin is needed whenever a preference is claimed and is named in the DFT conditions we reviewed. A phytosanitary certificate from the origin country's plant protection authority may be required by the DOA, which you confirm directly. The DFT permission or in-quota certificate and the DOA permit must be in hand before arrival, and an FDA licence is attached when it applies.
Two non-regulatory documents deserve attention. The first is a written quality agreement: sample approval, moisture and grade specification, defect tolerance and the right to reject, because these protect the buyer if the beans arrive damaged or off-grade. The second is cargo insurance. Coffee in bags can suffer from sea water, condensation or contamination, and an all-risks policy or a named-perils policy treats those differently; our articles What is cargo insurance and All-risks versus named-perils marine cargo insurance explain the difference, and How to file a cargo insurance claim shows what evidence you will need if something goes wrong.
Before the supplier ships, send a draft of the invoice and packing list to your customs broker. A five-minute check by someone who files declarations catches the mismatches that otherwise appear at the port.

How should green coffee be packed, loaded and shipped?
Green coffee is a dry, bagged agricultural cargo that is sensitive to moisture and odour. It absorbs water vapour from the air, which can raise its moisture content and encourage mould, and it takes on smells from the container, from other cargo and from fumigants. The standard answer in the trade is a dry container (a general-purpose box) with a clean, dry, odour-free floor and walls, plus measures against condensation. A container moving from a cool origin to a warm, humid destination can drip from the roof as the air inside cools and warms, a problem often called container rain, so exporters commonly use liners, kraft paper and ventilation or desiccant measures. The mix you choose should be agreed with the supplier and your forwarder; we are not prescribing a specific product.
Before stuffing, inspect the container for holes, previous cargo residue, dampness and smell; our Container inspection checklist lists what to look at. Bags should be stacked so that they are stable and do not press on the doors, and the supplier should provide a stuffing record with the container and seal numbers so that the numbers on the bill of lading match the box that arrives. If you import by sea, a full container load (FCL) gives a sealed box with one shipper's cargo, while less-than-container-load (LCL) consolidation shares a box with other cargo and exposes coffee to odour and handling from strangers. Our guides What is FCL shipping and FCL versus LCL shipping explain the trade-off.
Because coffee is not usually treated as a perishable cold-chain cargo, a refrigerated container is not the default, but some exporters ask for temperature management on long transits; discuss this with the supplier rather than assuming it. Air freight is possible for small, high-value lots such as samples, and our Air freight service page describes how that works, but for commercial volumes sea is the usual mode.
Document set to assemble before the goods ship
Commercial invoice and packing list
Description, quantity and weights must agree with every permit.
Bill of lading or air waybill
Consignee name and notify party match the importer on the permits.
Certificate of origin
Named in DFT conditions and needed if a preference is claimed.
Phytosanitary certificate
Issued by the origin plant protection authority where the DOA requires it.
DFT permission or quota certificate
In hand before arrival, matched to HS code and quantity.
DOA permit and FDA licence where they apply
Confirm each in writing with the agency.
Quality sample approval and insurance
Moisture and grade agreed before shipment; cargo insurance certificate on file.
Which Incoterm and contract terms protect a coffee importer?
The Incoterm decides who arranges the carriage, who clears export and import, and where risk passes from seller to buyer. For a first coffee import into a country with controlled imports, the Thai buyer usually wants to hold the permits, so terms where the buyer arranges the main carriage and import clearance, such as FOB, are common, while terms where the seller books the sea freight, such as CIF, put the booking in the supplier's hands and make it harder to control the container and the sailing. Our guides What are Incoterms, CIF versus FOB Incoterms and Choosing Incoterms for SMEs explain the differences; whichever term you choose, write the named port in the contract.
Tie the contract to the permits. State that the shipment is conditional on the importer's permits being in place, name the origin and the exporter exactly as they will appear on the invoice, and specify the quantity per container. Add the quality terms: moisture and grade specification, a pre-shipment sample approved by you, a rejection procedure and what happens to a lot that fails. Payment terms are a commercial matter; we do not recommend a structure here, but they should not release the final payment before the permits and documents are confirmed to match.
Finally, decide who is responsible for cargo insurance and make sure the policy covers the whole journey from the supplier's warehouse to yours, including inland legs. If the Incoterm leaves insurance to the seller, check the level of cover instead of assuming it is adequate.

When should you talk to a forwarder, and what can Thai Global Freight do?
Talk to a forwarder at the start, not when the container is already booked. The forwarder cannot issue the DFT, DOA or FDA permissions, and no forwarder should claim to, but a forwarder who handles imports can tell you what the broker will need at arrival, which port and terminal suit your cargo, how the container should be inspected and sealed, and how the documents should line up. That conversation often reveals a mismatch in the contract before it becomes a delay.
Thai Global Freight can help with the logistics and filing around your permits. Our import services page describes how we coordinate an import from origin to Thai warehouse, our customs clearance service covers the declaration and the attachment of permits, our sea freight and FCL pages describe container booking from origin ports, and our door-to-door shipping option arranges the inland leg to your site. If you are still comparing providers, our guide on choosing a freight forwarder in Thailand lists the questions to ask. To start, send us the origin country, the planned quantity, the target port and the permit status, and ask for a quote. We will tell you what we can arrange and what must stay with the agencies, and we do not quote rates in articles because they depend on your cargo and lane.
Before you contact us, have ready the supplier's name and country, the HS code you expect, the draft Incoterm, any written answers from the DFT, DOA and FDA, and the date by which you need the beans in your warehouse.
Common Mistakes
- Paying the supplier a deposit before the DFT route, quota position and plant quarantine status are confirmed in writing.
- Treating the forwarder or the supplier as the authority on whether coffee may be imported, instead of asking the DFT, DOA and FDA directly.
- Letting the importer name, exporter name or quantity differ between the permits, the invoice and the bill of lading.
- Loading green coffee into a damp or odorous container, or into an LCL box with strong-smelling cargo, and then discovering the damage at the warehouse.
- Relying on outdated slides or press reports for rules and quota windows instead of the current agency announcement.
What You Need to Prepare
- A registered Thai importer and a licensed customs broker with a power of attorney.
- Written confirmation from the DFT of the permission route for your origin and product, and the in-quota certificate if that route applies.
- A DOA plant quarantine permit, and a phytosanitary certificate from the origin country if the DOA requires one.
- The Thai FDA's written position on whether your use needs a food import premises licence.
- A supplier contract with the named origin, exporter, quantity, Incoterm, quality specification and sample approval.
- A container plan covering inspection, liners or moisture control, seal numbers and a cargo insurance policy.
Frequently Asked Questions
Do I need a permit to import green coffee beans into Thailand?
Yes, in the material we reviewed coffee is a controlled import managed by the Department of Foreign Trade, and plant quarantine is handled separately by the Department of Agriculture. Whether you also need an FDA premises licence depends on your use. Confirm the current conditions in writing with each agency before you place an order.
What is the HS code for green coffee beans in Thailand?
Unroasted coffee that has not had the caffeine removed is classified under HS 0901.11 in the international Harmonized System. The Thai national tariff line extends that code, so ask your customs broker to confirm the exact line and, if there is doubt, request an advance ruling from Thai Customs.
What is the WTO in-quota route for coffee imports?
It is an allocation of a set quantity of certain agricultural goods that enter at the lower in-quota duty rate. In the material we read, the DFT allocates it and an approved applicant receives a certificate of in-quota tax entitlement. We did not verify the current coffee quota list, so ask the DFT whether your product and origin qualify and when the application window opens.
Can I import green coffee beans as an air freight shipment?
Air freight is possible for small lots such as samples, and the same permits and customs rules apply as for sea freight. For commercial volumes, sea freight in a dry container is the usual mode. Confirm with the DOA whether samples need a separate permit or exemption before you send them.
Should I use FCL or LCL for green coffee?
Choose FCL when the volume fills a container or when odour and moisture protection matter most, because the box holds one shipper's cargo and you control the inspection and seal. LCL shares a box and exposes coffee to other cargo, so use it only for small lots after checking what else is loaded.
Does the freight forwarder get the import permit for me?
The permits are issued by the DFT, DOA and FDA, and the importer is the applicant. A forwarder or customs broker can explain what each agency asks for, prepare supporting documents and file the customs declaration, but should not be described as the issuer of a permit. Check what service scope any provider offers in writing.
Sources
- Department of Foreign Trade: WTO in-quota import announcement (Smart-I application and allocation)
- Department of Foreign Trade: briefing slides on controlled imports (June 2020)
- Department of Agriculture: National Single Window manual for import permit operators
- Thai FDA Food Division: food import entrepreneur guidance