Industrial machinery, illustrating Importing Machinery from China: Beyond Normal Container RulesThai Global Freight

Importing Machinery from China: Beyond Normal Container Rules

Importing a single production machine from a Chinese supplier: dimensions and weight against container limits, crating, documents, unloading and installation.

Author: Thai Global Freight Editorial TeamReviewed by: Thai Global Freight Editorial TeamPublished: 2026-09-14Updated: 2026-09-14Last verified: 2026-09-14

Quick Answer

Importing a production machine from China is a different problem from importing cartons of product, because a machine is usually one indivisible unit rather than cargo that can be split across pallets. Before anything is booked, you need the supplier's crated dimensions, gross weight, centre of gravity, and lifting-point data to know whether it fits a standard container, needs a flat rack or open top, or has become out-of-gauge or breakbulk cargo. From there, crating and moisture protection, documentation for the machine plus any spare parts or tooling, destination unloading and lifting, installation and commissioning by the supplier's engineers, and insurance for a single high-value unit all need to be planned before a deposit is paid — not discovered after the machine has already left the factory.

Key Takeaways

  • A single machine breaks the normal FCL assumption because it's usually one indivisible unit — dimensions and weight, not carton count, decide the shipping mode.
  • Get crated dimensions, gross weight, centre of gravity, lifting points, and disassembly options from the supplier before booking — a product brochure is not shipping data.
  • Crating, wood packaging treatment, and shock/moisture protection are separate from the shipping mode decision and need to be specified in the purchase agreement.
  • A machine plus spare parts and tooling shipped together can raise classification questions — resolve them with a licensed customs broker, not by guessing.
  • Destination unloading, lifting, installation, and insurance are commercial decisions that need to be planned before booking — not solved on arrival day.

Buying a production machine from a supplier in China and shipping it to Thailand looks, on paper, like any other import: get a quote, book a container, clear customs, take delivery. In practice, it's a different kind of shipment from the cartons-on-pallets cargo that most FCL and LCL thinking is built around. A machine is usually one thing — a single, heavy, oddly shaped, expensive unit that either fits inside a container or it doesn't, and that either survives a rough lift or it gets damaged trying. There's no splitting it across two boxes to solve a dimension problem, and no averaging its risk across dozens of cartons the way a general cargo shipment can.

That single fact changes almost everything downstream: how you talk to the supplier, what you need from them before you agree a price, how the freight is booked, how customs paperwork is prepared, how the unloading is planned, and what insurance actually needs to cover. This article walks through that chain in order, from the first question you should be asking the supplier through to the checklist worth running before any deposit leaves your account.

Key points at a glance

Summary panel listing the key points covered in this article on importing production machinery from China.
  • A single machine is not a scaled-up carton shipment — it's usually one indivisible, heavy, awkwardly shaped unit, so the normal FCL/LCL way of thinking about a container doesn't automatically apply.

  • Whether the shipment stays a standard FCL box, moves to a flat rack, or becomes out-of-gauge/breakbulk depends on dimensions and weight the supplier must confirm — not on a guess.

  • Crated dimensions, gross weight, centre of gravity, and lifting points must come from the supplier before booking — a factory data sheet is not shipping data.

  • Documentation for a machine plus its spare parts and tooling can raise classification questions that only a licensed customs broker should resolve.

  • Unloading, lifting, installation, and insurance all need to be planned before a deposit is paid — not solved on the day the truck arrives.

Ordinary FCL thinking runs on cartons or pallets: you know the CBM, you know the weight, you pick a 20-foot or 40-foot box, and the container absorbs the difference between the theoretical calculation and reality with a bit of spare space or a slightly loose stow. That flexibility disappears with a single crated machine. There's no stacking it differently to make it fit, no combining it with other cargo to use up leftover space, and no rounding the numbers because "it should be close enough." Either the crate's outer dimensions and weight sit inside what the container and the carrier's equipment can handle, or the shipment has to move to a different kind of booking entirely — a flat rack, an open top, or a breakbulk/heavy-lift vessel slot.

This is the first mental shift worth making before requesting a quote: stop asking "what container do I need for one machine" and start asking "what are this machine's actual shipping dimensions, weight, and shape, and which of the available options can carry that." The second question can only be answered once real numbers exist, and those numbers come from the supplier, not from a guess based on the machine's technical specification sheet.

Standard containers have published, standardised internal dimensions and door openings — that's true of every 20-foot and 40-foot general-purpose or high-cube box built to the ISO container standard, which is exactly why the shipping industry can move so much cargo through so few box types. A 20-foot general-purpose box and a 40-foot high-cube box each have a fixed internal length, width, and height, and a door opening that is narrower and shorter than the internal box itself. On top of the space question, every container also carries a maximum gross weight rating stamped on its CSC (Container Safety Convention) plate; subtract the container's own tare weight from that rating and what's left is the usable payload for whatever goes inside.

Those two published facts — internal envelope and rated payload — are the first filter for any machine. A crate that clears the internal length, width, and height but is too wide or tall to pass through the door still can't be loaded as a standard box shipment, even though it would technically "fit" once inside. A machine that is small enough to fit the box but heavier than that specific container's rated payload has the same problem from the opposite direction. And even a machine that clears both space and total weight can still overload the floor locally if all of that weight rests on a small footprint — a narrow base or a few point contacts — which is why forwarders sometimes ask for a spreader frame or a reinforced skid even on cargo that is, on paper, within the container's numbers.

Where a machine can outgrow a standard container

Schematic naming the internal dimensions and door opening of a standard container, showing that a crate can be too long, too wide, too tall for the box, or too tall/wide only for the door, or too heavy for the box's payload even when it fits.

Internal box length, width, height

The crate's outer dimensions must clear all three — a machine that's a few centimetres too long, wide, or tall for the box rules out a standard dry container entirely

Door opening (narrower and shorter than the box itself)

A crate can be narrow enough for the box but too wide or tall to pass through the door — this is the most commonly missed constraint

Rated payload (max gross weight rating minus the box's own tare weight)

A machine can be small enough to fit a box yet still exceed what that specific container is rated to carry — always confirmed against the individual box's CSC plate

  • Floor point-loading — A heavy machine resting on a small footprint (a few feet or a narrow base) can locally overload a standard floor even when the total weight is within the box's rating, which is why a spreader or skid is often needed

When a machine breaks through any of those limits but the overage is manageable, the usual next step is a flat rack container — a platform with end walls but no side walls or roof, built for cargo that's over-width, over-height, or too irregular a shape to fit through a standard door. Because there's nothing in the way, a flat rack is loaded from the top or the side by crane, and the cargo is secured with chains or straps to lashing points along the deck edges rather than being enclosed. This solves the door and side-wall problem completely, since there's no door and no wall to clear — the constraint shifts instead to the vessel's own stowage limits and to whatever height or width restriction applies once it's loaded on deck. A closely related option, an open top container, keeps side walls but removes the roof in favour of a tarpaulin or hard cover, which suits cargo that's over-height but not over-width. Full detail on how a flat rack is built, secured, and typically used sits in a dedicated article: what is a flat rack container.

When the machine's dimensions extend past the flat rack's own deck length or width — protruding over the ends or hanging off the sides — the shipment crosses into out-of-gauge (OOG) cargo, a formal category that shipping lines and ports treat differently from standard-envelope cargo because it needs special stowage on the vessel, extra clearance from neighbouring containers, and sometimes a different crane or berth. And when the unit is too heavy or too oddly shaped to sit safely on a flat rack's deck at all — regardless of dimensions — the shipment moves further still, into breakbulk or heavy-lift territory, where it's no longer handled as a containerised box at all but as standalone cargo lifted, lashed, and stowed directly on a vessel built or fitted for that kind of load. Both of these categories carry real planning consequences: booking lead times, lifting-plan requirements, and vessel or berth availability all work differently once a shipment leaves the world of standard containers. Two dedicated articles cover each in depth — what is OOG cargo and how heavy-lift cargo is shipped — and either is worth reading in full once a machine's numbers start suggesting it won't be a simple container booking.

Industrial machinery in practice, illustrating Importing Machinery from China: Beyond Normal Container Rules
Industrial machinery in practice, illustrating Importing Machinery from China: Beyond Normal Container Rules — Thai Global Freight

None of that classification work can happen without real numbers, and this is where a surprising number of machinery imports stumble: the buyer has a technical specification sheet from the supplier — footprint, power rating, output capacity — but not a single figure that describes how the thing actually ships. A technical spec sheet is written to sell the machine's performance, not to plan its transport. It rarely states the crated outer dimensions, almost never states the packed gross weight including the crate itself, and essentially never mentions centre of gravity or lifting points, because none of that matters to someone evaluating whether the machine can do the job on the factory floor.

So the practical task is asking for that data explicitly and early, ideally before final commercial terms are agreed, since the shipping mode it points to can materially change the freight cost baseline the buyer is comparing quotes against. The list to request is short but specific: crated (packed) outer dimensions in length, width, and height; gross weight of the crate as it will actually be lifted, not the bare machine weight; the location of the centre of gravity, since an asymmetric machine rarely balances at its geometric middle; the number, type, and position of lifting or sling points, ideally as a marked drawing rather than a verbal description; and whether the unit ships assembled as one piece or breaks down into separate sub-assemblies for transport. Reputable industrial equipment manufacturers that export regularly can usually produce this information without much delay, because their own logistics partners in China ask for exactly the same things — a supplier who can't answer these questions at all is itself a signal worth noting before a deposit is committed.

Centre of gravity and lifting-point data matter for a reason that's easy to underestimate from behind a desk: a crane operator rigging an unfamiliar crate has to guess where the weight sits unless they're told, and a wrong guess on an off-centre load can mean the crate tips, swings unpredictably, or puts uneven strain on slings that were sized for a symmetric lift. A proper lifting plan or rigging drawing from the supplier — showing sling angles, spreader bar requirements if the load is wide or the centre of gravity is high, and which marked points are rated to carry weight versus which are just structural crate members — turns that guesswork into a repeatable, checkable procedure. It also gives the destination port or site the information it needs to plan the lift in advance rather than working it out cold when the crate is already hanging from a hook.

Shipping data to collect from the supplier before booking

Checklist of shipping-specific data a machinery buyer needs from the Chinese supplier: crated dimensions and gross weight, centre of gravity, lifting points, and whether the machine disassembles.
  • Crated (packed) dimensions and gross weight

    Not the machine's bare footprint — the outer envelope and weight of the crate or skid as it will actually travel

  • Centre of gravity

    Where the weight actually sits inside the crate, which is rarely dead-centre on an asymmetric machine

  • Number and location of lifting/sling points

    Marked on the crate or supplied as a drawing, so a crane operator can rig it correctly without guessing

  • Whether the machine disassembles, and into how many pieces

    Can change the shipping mode entirely — several smaller crated units may fit standard containers where one assembled unit could not

Whether the machine disassembles is worth asking early precisely because it can flip the entire shipping-mode decision. A machine that ships as one welded, fully assembled frame might be an OOG or breakbulk case on its own numbers, while the same machine broken down into a base, a tower or column, a control cabinet, and a set of ancillary components might travel as several ordinary crates inside a single standard container — cheaper to book, simpler to insure, and far less demanding to unload. The trade-off is that disassembly shifts more of the reassembly and alignment work to the destination, which usually means the supplier's own engineers need to be involved in commissioning rather than a local rigger simply setting a single unit in place. Neither option is automatically better; the point is that this is a decision to make deliberately, with both the freight cost difference and the installation implications on the table, not something to discover by accident when the supplier ships however they normally ship.

Industrial machinery in practice, illustrating Importing Machinery from China: Beyond Normal Container Rules
Industrial machinery in practice, illustrating Importing Machinery from China: Beyond Normal Container Rules — Thai Global Freight

Once the shipping mode is settled, crating becomes its own set of decisions rather than an afterthought. An export crate for industrial machinery does real structural work: it distributes the load onto the points a crane or forklift is meant to lift from, keeps the machine rigid against the shocks and vibration of road, sea, and repeated handling, and protects machined surfaces, control panels, and painted finishes from scratching, denting, and contact damage. Crates for this kind of cargo generally come in a few recognisable forms — a fully enclosed crate for units with delicate surfaces or electronics that need full weather protection, an open (skeleton) crate for bulkier, more robust machinery where full enclosure isn't necessary and visibility for inspection is useful, and a skid-mounted arrangement for a unit that's simply bolted to a heavy timber or steel base for lifting and securing without a full surrounding structure. Which form suits a given machine is a conversation to have with the supplier's packing team, not a default to accept without asking.

Wood packaging used in international cargo is a widely applied treatment standard, since untreated solid wood packaging material can carry pests between regions — most reputable Chinese suppliers already use certified, treated wood or engineered/plywood alternatives for export crates as standard practice, and stamp the crate accordingly. The exact certification requirement, marking, and any inspection process that applies on entry into Thailand is a jurisdictional detail that changes by cargo type and current rule, so it should be confirmed with your customs broker or forwarder rather than assumed from what worked on a previous shipment — but asking the supplier upfront to confirm their wood packaging is treated and marked to the applicable international standard is a reasonable, low-effort request to make before crating begins.

Beyond the crate structure itself, a machine spends weeks in transit exposed to vibration, tilt, temperature swings, and humidity, and each of those needs its own protection layer. Vibration and shock indicators (tilt watches or shock loggers) attached to the crate give a record of any rough handling event during transit, which matters both for catching a problem early and for supporting an insurance claim if damage shows up later. Bare or machined metal surfaces need corrosion protection — rust-preventive coating or wrapping — particularly relevant given the humidity a shipment passes through en route to and within Thailand. Desiccant and a vapour-barrier wrap inside the crate control moisture that would otherwise condense inside an enclosed space during temperature changes between day and night or between climates. Control cabinets, electrical panels, and sensitive instrumentation should be sealed and, where practical, have any removable modules taken out and packed separately with clear labelling for reinstallation. And any hydraulic or pneumatic lines should be drained, capped, or otherwise secured so that fluid doesn't leak in transit or pressure doesn't build in a sealed line during temperature changes. It's also worth photographing the machine's condition — paint, surfaces, any pre-existing marks — before it's crated, since that record is exactly what an insurer will ask for if a damage claim is ever filed.

Industrial machinery in practice, illustrating Importing Machinery from China: Beyond Normal Container Rules
Industrial machinery in practice, illustrating Importing Machinery from China: Beyond Normal Container Rules — Thai Global Freight

Documentation for a machinery shipment carries its own layer of complexity that a general cargo shipment doesn't. The commercial invoice needs to state the actual transaction value of the machine — the real price agreed with the supplier — since that value is what customs and insurance both work from, and understating it to reduce a perceived cost exposure creates a mismatch that can cause problems on both sides rather than saving anything. When spare parts, tooling, jigs, or accessories travel in the same shipment as the machine, each item needs to appear clearly on the packing list and invoice with its own description and value, rather than being folded into a single lump-sum line for "machine and accessories." Vague or bundled descriptions are one of the more common reasons a shipment gets held for clarification at clearance, simply because the officer reviewing it can't tell what's actually inside the crates from the paperwork alone.

From deposit to commissioning: what to plan and when

Ordered stages of a machinery import from confirming shipping data with the supplier, through documentation, booking and destination-lift planning, to installation and commissioning.
  1. 1

    Confirm shipping data with the supplier

    Crated dimensions, gross weight, centre of gravity, lifting points, disassembly option — before any deposit

  2. 2

    Decide the shipping mode with your forwarder

    Standard container, flat rack, open top, or breakbulk/heavy-lift booking, based on the confirmed data

  3. 3

    Prepare documentation

    Commercial invoice at real value, packing list itemising every crate and any spares or tooling, classification confirmed with a broker

  4. 4

    Plan the destination lift

    Confirm crane or forklift access, site clearance, and who supplies the lifting gear, before the vessel is booked

  5. 5

    Installation and commissioning

    Coordinate the supplier's engineer travel with the machine's arrival so neither sits waiting idle

There's a classification layer sitting behind that documentation question too: a complete machine, the spare parts shipped with it, and any specialised tooling can each sit under a different customs classification, and whether spares travelling with a machine are treated as part of the machine or as separate goods in their own right is exactly the kind of determination that depends on the specific machine, the specific parts, and the current classification rules applied at clearance. This is not a decision to make by pattern-matching against a previous shipment or a supplier's own assumption about how it should be declared — it belongs with a licensed customs broker who can review the actual items and confirm the correct treatment before the shipment departs China, not after it's already sitting at a Thai port waiting on a clarification request.

Everything up to this point has been about getting the machine to Thailand safely and with clean paperwork. What happens the moment it arrives is a separate planning problem, and it's one that has to be worked out before the booking is confirmed, not after the container is already on a truck heading to site. The core question is simple to ask and easy to skip: does the delivery site have the crane, forklift, or gantry capacity to take the machine off the truck or out of the container, and does the route into the site — gate width, overhead clearance, road surface, turning radius for a flatbed — actually allow the load to get there in the first place? A factory that can run its production line perfectly well may still have no way to lift a ten-tonne crate off a flatbed trailer, or a gate too narrow for the trailer itself to enter.

Where the site itself can't handle the lift, the usual workaround is to route the crate through a yard, warehouse, or port facility that has the right equipment, unload it there, and re-position it onto site-appropriate transport for the final leg — which adds a step, a handling point, and a cost that needs to be quoted and agreed in advance rather than discovered as a surprise charge once the crate is already in the country. Whoever ends up responsible for supplying the lifting gear — the forwarder, a specialised rigging contractor, or the buyer's own facilities team — needs to be identified and the arrangement confirmed as part of the shipment plan, with that scope and cost as a stated line item in the freight quote rather than an assumption left unspoken until the delivery date. Treating this as a booking-stage decision rather than a delivery-day problem is, in practice, the single biggest difference between a machinery import that lands smoothly and one that sits on a truck outside a factory gate while everyone works out what to do.

Industrial machinery in practice, illustrating Importing Machinery from China: Beyond Normal Container Rules
Industrial machinery in practice, illustrating Importing Machinery from China: Beyond Normal Container Rules — Thai Global Freight

Installation and commissioning are worth pulling out as a separate commercial question from freight, because they're easy to assume are included in the machine's purchase price when they often aren't. Whether the supplier sends their own engineers to Thailand to install, align, and commission the machine — and whether that support is bundled into the purchase price, offered as a paid add-on, or not offered at all — needs to be a specific term in the purchase agreement, not an assumption carried over from how a smaller, simpler purchase might have worked. If the supplier's engineers are travelling, their visa and work authorisation arrangements are a matter to confirm directly with them and, where relevant, with Thai immigration requirements for foreign technical personnel — a jurisdictional detail to verify rather than assume based on how it worked for a different supplier or a different country. And because warranty terms on complex machinery are frequently tied to the machine having been installed and commissioned under the supplier's own supervision, skipping that step to save cost can quietly void a warranty that the buyer is counting on.

Timing matters here too: the supplier's engineer travelling on a fixed schedule and the machine's actual arrival date need to line up, since an engineer arriving to an empty factory floor because the shipment is delayed, or a machine sitting uninstalled for weeks because the engineer's schedule doesn't match, both turn a planning gap into wasted time and cost. Coordinating those two schedules is a conversation to have explicitly with the supplier once a realistic shipping timeline exists — not something to leave until the machine is already at sea.

Checklist before paying a deposit

Checklist a buyer should complete with the supplier, forwarder, and broker before committing funds to a Chinese machinery purchase.
  • Crated dimensions, gross weight, and centre of gravity confirmed in writing

  • Shipping mode (standard/flat rack/open top/breakbulk) checked against that data with your forwarder

  • Crating, treatment, and shock/moisture protection specified with the supplier

  • Invoice value, spare parts, and tooling itemised and reviewed with a customs broker

  • Destination crane/forklift access and site clearance confirmed

  • Installation, commissioning, and insurance basis agreed in writing

Insurance for a single high-value machine deserves its own scrutiny rather than defaulting to whatever general cargo policy a forwarder offers as standard. A policy built around spreading risk across many mid-value cartons in a consolidated shipment is answering a different question from a policy covering one indivisible unit whose entire value is concentrated in a single lift, a single stow point, and a single set of handling events. Worth checking specifically: whether the policy's declared value reflects the machine's full replacement cost plus freight and any installation expense already committed, rather than just the ex-works purchase price; whether loading and discharge lifting operations — the point at which damage most often actually occurs on this kind of cargo — are explicitly covered rather than assumed; and whether the policy distinguishes between total loss and partial damage in a way that matches how a single-unit shipment would actually fail, since a dented panel and a cracked casting are very different outcomes for a one-off machine than for a shipment of many identical cartons where damage to a few units barely dents the total claim. These are the right questions to put directly to whoever is arranging the cargo insurance, before the policy is bound rather than after a claim is being filed.

Pulling all of this together, the practical sequence for a machinery purchase looks different from an ordinary product-sourcing shipment in one important way: several decisions that would normally be settled after a deposit is paid need to be settled before it, because they change what the freight actually costs and how the machine actually gets delivered. Confirm the crated dimensions, gross weight, centre of gravity, and lifting points with the supplier. Decide, with a forwarder, whether that data points to a standard container, a flat rack, an open top, or an OOG/breakbulk booking. Agree the crating standard, wood packaging treatment, and shock/moisture protection in writing as part of the purchase terms. Get the commercial invoice value, spare parts, and tooling itemised properly and reviewed by a customs broker before shipment. Confirm the destination site can actually receive and lift the crate, or arrange an intermediate unloading point if it can't. Settle installation and commissioning responsibility and timing with the supplier as a named contract term. And check that the cargo insurance in place actually matches the risk profile of a single high-value unit rather than a general cargo policy applied by default. None of these steps requires guessing at a number that isn't known yet — each one is a question to put to the right party, in the right order, before money changes hands.

Common Mistakes

  • Booking a standard container slot before getting crated dimensions, gross weight, and centre-of-gravity data from the supplier, then discovering the crate doesn't fit or overloads the box.
  • Treating a technical specification sheet as if it were shipping data, when it rarely states packed dimensions, gross weight, or lifting points.
  • Bundling spare parts and tooling into a single vague line on the invoice and packing list, which invites clarification delays at customs.
  • Assuming installation and commissioning by the supplier's engineers are automatically included in the purchase price, without a written term to that effect.
  • Buying a general cargo insurance policy for a single high-value unit without checking whether loading/discharge lifting operations are explicitly covered.
  • Not confirming crane, forklift, or access capability at the Thailand delivery site until the truck is already there.

What You Need to Prepare

  • Supplier-confirmed crated dimensions, gross weight, centre of gravity, and lifting-point data (ideally a rigging drawing).
  • A commercial invoice reflecting the actual machine value, with any spare parts or tooling itemised separately.
  • A packing list identifying every crate or skid and exactly what it contains.
  • A confirmed destination lifting and access plan before the shipment is booked.
  • A written scope covering whether and how the supplier's engineers support installation and commissioning.
  • Confirmation from your freight forwarder or customs broker on the correct shipping mode and classification treatment.

Frequently Asked Questions

How do I know if my machine needs a flat rack instead of a standard container?

Compare the crate's outer dimensions and weight against the standard container's internal box, door opening, and rated payload — not the machine's bare footprint. If the crate clears the internal space but is too wide or tall for the door, or the weight exceeds that specific box's rated payload, it typically moves to a flat rack or open top. Your forwarder can confirm this once the supplier provides crated dimensions and gross weight.

What is out-of-gauge (OOG) cargo and when does my machinery count as OOG?

OOG cargo is cargo whose dimensions extend beyond a container's or flat rack's normal envelope — for example, protruding over the ends or sides of a flat rack's deck. It's treated as a formal category by shipping lines and ports because it needs special stowage and clearance. Full detail is covered in a dedicated article: what is OOG cargo.

Who determines the shipping weight and centre of gravity of the machine — me or the supplier?

The supplier provides this data, since they control how the machine is crated and packed. It's the buyer's job to ask for it explicitly and early — ideally as a rigging drawing showing lifting points — because a technical spec sheet almost never includes it.

Should spare parts and tooling be declared on the same invoice as the machine?

They can travel in the same shipment, but each item should be itemised separately on the packing list and invoice with its own description and value, rather than folded into one lump-sum line. Whether they're classified together with the machine or separately is a customs classification question your broker should confirm before shipment.

Do I need to arrange the crane at the Thailand delivery site myself?

Someone has to — a forwarder, a specialised rigging contractor, or your own facilities team — and that responsibility needs to be agreed and quoted before the shipment is booked, not decided on delivery day. If the site itself can't handle the lift, the crate may need to route through a yard or warehouse with the right equipment first.

Is installation by the supplier's engineers included in machinery freight?

No — installation and commissioning are a separate commercial matter from freight, covering the machine's transport only. Whether the supplier's engineers install and commission the machine, and whether that's bundled into the purchase price or charged separately, needs to be a specific written term in the purchase agreement.

Can I use a normal cargo insurance policy for a single expensive machine?

You can, but it's worth checking first whether the declared value reflects the machine's full replacement cost plus freight and installation, whether loading/discharge lifting operations are explicitly covered, and whether the total-loss versus partial-damage terms actually fit a single indivisible unit rather than a consolidated shipment of many cartons.

What should I confirm before paying a deposit to a Chinese machinery supplier?

At minimum: crated dimensions, gross weight, centre of gravity, and lifting points; the shipping mode this points to; crating and wood packaging treatment; how the invoice will itemise the machine, spares, and tooling; whether the destination site can receive and lift the crate; installation/commissioning terms; and whether your cargo insurance fits a single high-value unit.